Transformer Sizing Calculator

Enter the load and voltages to get the standard kVA size, primary and secondary full-load amps and protection ratings.

kVA = V × I / 1000 (1φ)  •  kVA = √3 × V × I / 1000 (3φ)  •  I = kVA × 1000 / (√3 × V)
Calculated Result
—

Step-by-step

  1. Enter valid values to begin.

Standard kVA sizes follow common dry-type and pad-mount ratings (1-phase: 1, 1.5, 2, 3, 5, 7.5, 10, 15, 25, 37.5, 50, 75, 100, 167 kVA; 3-phase: 3, 6, 9, 15, 30, 45, 75, 112.5, 150, 225, 300, 500, 750, 1000 kVA). Primary and secondary protection follow NEC 450.3(B) for transformers 1000 V and below with primary-only or primary-plus-secondary protection rules summarised below.

IEEE C57 • NEC 450.3(B) • Transformer Sizing & Protection

Transformer Sizing: kVA, Full-Load Amps and Overcurrent Protection

Core Engineering Principles

A transformer is rated in kVA, not kW, because the copper and iron inside it heat according to current and voltage, regardless of the power factor of the load. That’s why you divide kW by power factor first. It also means a transformer feeding a poor power-factor load can be overloaded while the wattmeter reads fine. Add up the load in kVA, add margin for growth, and pick the next standard size up. A common practice is to add 20–25% for future growth, and not to size a transformer to exactly 100% of the load.

Full-load amps follow directly from the kVA and voltage: I = kVA × 1000 / V for single-phase, and divide by 1.732 as well for three-phase. You need that current on both sides. The primary current sizes the primary protection and feeder, the secondary current sizes the secondary conductors and panel. Remember the primary current is smaller because the primary voltage is higher.

1φ: I = kVA × 1000 / V  •  3φ: I = kVA × 1000 / (√3 × V)
Required kVA = Load kVA × (1 + growth %)  •  OCPD (450.3(B)): primary 125% (167% if under 9 A), secondary 125%

NEC & Standard References

NEC 450.3(B) covers transformers rated 1000 V or less. With only primary protection, the device must be no more than 125% of the primary rated current when the current is 9 A or more, 167% if between 2 and 9 A, and 300% if under 2 A. You can use the next higher standard size from 240.6 if 125% doesn’t land on one. If you also protect the secondary at 125% (167% if under 9 A), the primary device may go up to 250%. 450.9 requires ventilation clearance, 240.21(C) governs secondary conductor tap rules, and 450.13 covers accessibility. Standard 3-phase sizes are 15, 30, 45, 75, 112.5, 150, 225, 300, 500 and 750 kVA.
Worked Example: 45 kVA Load on a 480 V to 208Y/120 V Transformer
Given: 45 kVA connected load, 25% growth, 3φ, 480 V primary, 208 V secondary.
1. Required: 45 × 1.25 = 56.25 kVA, so the next standard size is 75 kVA.
2. Primary FLA = 75,000 / (1.732 × 480) = 90.2 A.
3. Secondary FLA = 75,000 / (1.732 × 208) = 208.2 A.
4. Primary OCPD: 90.2 × 1.25 = 112.8 A → 125 A (next standard).
5. Secondary: 208.2 × 1.25 = 260.3 A → 300 A (next standard). Check that the secondary conductor can be protected by it.
Safety & Installation Rules
  • kVA, not kW. If the loads are mostly motors at 0.8 PF, 45 kW is 56 kVA before you add growth.
  • Inrush on energizing. A transformer can draw 8–12 times full-load current for a few cycles; time-delay fuses or breakers with an adjustable instantaneous setting help.
  • Harmonics. Nonlinear loads need K-rated transformers or oversizing, and the neutral may need to be doubled.
  • Clearances. Dry-type units need air space around them per the manufacturer; stuffing one in a closet is a common cause of overheating.
  • Ground the secondary properly. A separately derived system needs its own grounding electrode conductor and bonding jumper per 250.30.

Full-Load Current by Size (Three-Phase)

Three-phase full-load current I = kVA × 1000 / (√3 × V).
SizeAt 480 VAt 208 VAt 400 V
15 kVA18.0 A41.6 A21.7 A
30 kVA36.1 A83.3 A43.3 A
45 kVA54.1 A124.9 A65.0 A
75 kVA90.2 A208.2 A108.3 A
112.5 kVA135.3 A312.3 A162.4 A
150 kVA180.4 A416.4 A216.5 A
225 kVA270.6 A624.5 A324.8 A
300 kVA360.8 A832.7 A433.0 A
500 kVA601.4 A1387.9 A721.7 A

Single-Phase Current

Single-phase full-load current I = kVA × 1000 / V.
SizeAt 240 VAt 120 V
5 kVA20.8 A41.7 A
10 kVA41.7 A83.3 A
15 kVA62.5 A125.0 A
25 kVA104.2 A208.3 A
37.5 kVA156.2 A312.5 A
50 kVA208.3 A416.7 A
75 kVA312.5 A625.0 A

Standard Transformer Sizes

Standard sizes. Always round up.
TypeCommon ratings (kVA)
Three-phase15, 30, 45, 75, 112.5, 150, 225, 300, 500, 750, 1000
Single-phase1, 1.5, 2, 3, 5, 7.5, 10, 15, 25, 37.5, 50, 75, 100, 167

Standard Breaker and Fuse Ratings

Round up to the next size when the NEC allows it.

Common standard OCPD ratings (NEC 240.6).
Amps
15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, 100, 110, 125, 150, 175, 200, 225, 250, 300, 350, 400, 450, 500, 600

Worked Example: Small Shop on Single Phase

Load is 18 kVA with 25% growth, so the required size is 22.5 kVA and the next standard size is 25 kVA. Secondary full-load current at 240 V is 104.2 A. If the primary is 480 V, the primary current is 52.1 A, so the primary protection at 125% is 65.1 A, rounded to 70 A. Check the secondary conductor against its overcurrent device.

Transformer Sizing Questions

How do I size a transformer?

Add the connected load in kVA, add growth, and round up to the next standard size.

Why kVA and not kW?

The transformer carries current regardless of power factor, so its limit is in kVA.

How much growth should I allow?

Common practice is 20 to 25%. Adjust for planned loads.

What does 125% mean for protection?

Under NEC 450.3(B) the primary protection is usually up to 125% of the rated primary current, with higher values for small currents.

Do harmonics matter?

Yes. Nonlinear loads need K-rated units or oversizing, and the neutral may need to be doubled.

What is the inrush current?

8 to 12 times the full-load current for a few cycles when energised.